1. The "brush and burn" portion of Phase I is completely finished. THANK YOU to those of you that pitched in and gave of your time, energy and resources to get this done ahead of schedule!

2. The access drive is currently being covered with gravel. This driveway comes off of Bible Camp drive and runs east to west along the south side of camp's Eagles Nest building. This drive will be utilized by the construction vehicles and eventually, will be the main entrance to the new facility. In it's final stage, it will include a circle drive near the office portion of the Retreat Center.

3. From the building perspective, we need the Health Department to expediate their end of the permit approval process. Please pray for God's will to be done in this matter.